$50M out of inventory by finishing what we started
Lean on gas turbine parts at Siemens Energy. Dozens of workshops, half the WIP, 45% shorter lead times and $50M less inventory.
- Role
- Lean and operational excellence
- Context
- Siemens Energy, gas turbine manufacturing
- Period
- 2010 to 2018
- $50M inventory reduction
- 45% shorter lead times and 20% lower product cost
- Service rotor lead time cut from 18 weeks to 6
- WIP cut by 50%
- Monte Carlo inventory model saving $500K a year
The situation
Gas turbine parts are very expensive. A blade is a super clean Inconel casting, and then it takes a lot of machining time. Every part sitting half done on the floor is money sitting still.
Too much work was getting started and not finished. Queues grew. Lead times grew. Inventory piled up.
What I did
I was trained by Porsche consultants. I led a few dozen lean workshops and was the primary stakeholder on a few dozen more. The goal was lean, and the first step was simple.
Every workshop came back to one rule: stop starting work we weren't finishing. If the shop couldn't finish it, we didn't start it.
Then we got clear about single-piece flow.
We reworked the workstations so parts moved through one at a time instead of waiting in batches.
That is how we cut WIP in half and took service rotor lead time from 18 weeks to 6.
I also built a Monte Carlo model to optimize inventory. It saves $500K a year on its own.
What changed
- Inventory down $50M
- Lead times down 45%
- Product cost down 20%
- WIP down 50%
- Service rotor lead time from 18 weeks to 6
- $500K a year saved by the Monte Carlo model
Finish what you start, and the money shows up.
What it means for you
If your cash is tied up in half-finished work, the first fix is not more capacity. It is to stop starting and start finishing.